By Catharin Shepard • Editor • Over the past months, work crews have been clearing the way for the four-lane expansion of N.C. 211 between Raeford and Aberdeen, but when will the construction start – and when will it end?
The good news for people who just want to see it get done: the long-awaited widening will start in 2025, and nine miles of the newly four-lane road in Hoke County should be completed and open to drivers by December 2028.
The bad news for people dreading it: the second half of the roadway project has to work around the 2029 U.S. Open golf tournament, and that part of construction isn’t expected to be completed until 2034.
The North Carolina Department of Transportation (NCDOT) plans to let the contract for the first of two construction phases of the work in early 2025, according to Project Engineer Travis L. Morgan, the Division Construction Engineer for the N.C. Department of Transportation Division 8.
“Right now, where we currently stand, we are working on the clearing and grubbing, and erosion control contract for the entire length of the project,” Morgan said. “We started in Raeford and then we’ve cleared and grubbed and done the erosion control, and the dry utilities are relocating. That’s part of what the partner refers to as our pre-construction activities. That work will continue all the way up into Aberdeen, and then wrap that up.”
The project includes turning the road into a four-lane highway, including a median and improved intersection points. The R-5709 project consists of widening N.C. 211 to multi-lanes (four lanes divided) from US 15/US 501 in Aberdeen to SR 1244 (West Palmer Street)/SR 1311 (Mockingbird Hill Road) in Raeford.
The widening project is needed to accommodate future traffic volumes and improve safety, NCDOT officials have said. The currently two-lane road between Raeford and Aberdeen has been the scene of many injurious and fatal, often head-on accidents over the years.
The NCDOT decided to split the project into two parts, Morgan said. The first will be a large chunk of the construction to take place in Hoke County.
“As we proceed forward, the roadway contract has been split into two separate projects. The project that’s going to let in January 2025 is what we refer to as the section from just north of Ashemont Road, down to Raeford. I think it’s a little over nine miles,” Morgan said.
That project is in review phase right now and will be advertised for bid for eight weeks and will be let around mid-January of the coming year, he said.
“That project, the completion date of it would be by December 1 of 2028,” Morgan said.
The second part of the project, now known as R-5709-B, will continue the widening through from Aberdeen to around Ashemont Road, and will have to be scheduled around the 2029 U.S. Open golf tournament, which will take place in Pinehurst.
“Unfortunately, we couldn’t get both of the projects done during the U.S. Open timeline, so what we’ve had to do is split the project,” Morgan said. “The B section from Aberdeen to Ashemont, it will be let in July of 2029. The U.S. Open is in June, so as soon as the Open is complete, we will start the B section and it will have to be completed by late fall of 2034.”
At least, the first section of nine miles of four-lane divided road in Hoke should be opened for traffic by December 2028.
The entire corridor is over 15 miles long, and there’s “no way from a constructability standpoint to get all that work before the 2029 U.S. Open.”
“That was the reason we had to find a good point between the two jobs and stagger them. That’s our plan moving ahead,” Morgan said. “We’re looking forward to getting the first project going the first of next year.”